Physical Progress as on December 31, 2020

 

Item Status (%)
C-I Dam 90.40
C-II HRT (Head Race Tunnel) 99.08
C-III Power House 78.69
E&M Works (Electr0-mechanical) 79.31
Transmission 100.00
TOTAL 89.36