PHYSICAL PROGRESS
[/et_pb_text][et_pb_text admin_label=”Foo gallery 4577″ background_layout=”light” text_orientation=”left” use_border_color=”off” border_color=”#ffffff” border_style=”solid”]
[/et_pb_text][et_pb_divider admin_label=”Divider” color=”#4f4f4f” show_divider=”on” height=”2″ divider_style=”groove” divider_position=”center” divider_weight=”3″ hide_on_mobile=”on” /][et_pb_text admin_label=” Text physical progress table ” background_layout=”light” text_orientation=”left” use_border_color=”off” border_color=”#ffffff” border_style=”solid” text_font_size=”15″]
PHYSICAL PROGRESS OF THE PROJECT AS ON May 31, 2026
| Item | Status (%) |
| C-I Dam | 100 |
| C-II HRT (Head Race Tunnel) | 100 |
| C-III Power House | 99.58 |
| E&M Works (Electr0-mechanical) | 99.90 |
| Transmission | 100.00 |
| TOTAL | 99.98 |
[/et_pb_text][et_pb_divider admin_label=”Divider” color=”#4f4f4f” show_divider=”on” height=”2″ divider_style=”groove” divider_position=”center” divider_weight=”3″ hide_on_mobile=”on” /][et_pb_text admin_label=”Foo gallery 3936″ background_layout=”light” text_orientation=”left” use_border_color=”off” border_color=”#ffffff” border_style=”solid”]