I. Main Civil Works/Packages Including Hydro-Mechanical (HM) Works
C-1 DAM
Contract Package # C-1 :-Construction of Diversion Tunnel, Dam, Intake and Desilting Arrangement including Hydro-Mechanical works and Highway Tunnel
The construction work of Diversion Tunnel, Dam, Intake and Desilting Arrangement including Hydro-Mechanical works and Highway Tunnel was awarded to M/s Jaiprakash Associates Ltd. on June 26, 2011.
The Contract Package C-1 consists of following components:
- 1 No. Diversion Tunnel of 12 m dia., 877.46 m length & 1118 Cumec. Design Discharge
- Concrete Gravity Dam of 91 m height & 223.8 m length
- U/s Coffer Dam of 168.75 m length & 22 m height
- D/s Coffer Dam of 102.02 m length & 13.5 m height
- Chute with Gates type Auxiliary Spillway with 1 No. gate
- Sluice Spillway with 7 Nos. Gate, each of 8 m x 13.20 m
- 4 Nos. Intake Tunnels each of 6.4 m dia. & total length of 1926.78 m
- 4 Nos. underground Desilting Chambers each of 420 m (L) x 17/19 m (W) x 24.74 m (H)
- Silt Flushing Tunnel(D-shaped) of size 3.6 m (W) x 2.96 m (H) to 8.6 m (W) x4.675 m (H), 495 m length
- Highway Tunnel of 11 m dia., 1522 m length
Special Features / Uniqueness of the Package
- Diversion Tunnels (with 12 M dia) constructed is the largest in the sub-continent.
- Desilting Chambers are the biggest in size in the country.
- First ever Highway Tunnel (1.5 KM) constructed in Bhutan on the National Highway.
Important dates
SL. No. | Important Milestones Innaugration Details |
Dates |
1. | Punatsangchhu River was diverted through the Diversion Tunnel by Chief Advisior of Interim Government Hon’ble Lyonpo Sonam Tobgye. | 20.05.2025 |
2. | Dam concreting works commenced. | 01.12.2017 |
3. | Punatsangchhu River was diverted to its original course by Hon’ble Lyonpo Loknanth Sharma, Minister MoEA & His Excellenct Shri Sudhakar Delela, Ambassador of India to Bhutan. | 21.12.2022 |
4. | The dam concreting works successfully completed, paving way for subsequent phase of such reservior impoundment and power Genearation readiness. | 22.10.2022 |
5. | The reservoir filling commenced by the Hon’ble Prime Minister, Dasho Tshering Tobgay, along with the Minister for MoENR & the Ambassador of India to Bhutan. | 21.02.2024 |
6. | The reservoir reached its Full Reservoir Level (EL. 843m) marking a critical achievement in the project’s commissioning phase. | 13.01.2025 |