I.  Main Civil Works/Packages Including Hydro-Mechanical (HM) Works

C-1 DAM

Contract Package # C-1 :-Construction of Diversion Tunnel, Dam, Intake and Desilting Arrangement including Hydro-Mechanical works and Highway Tunnel

The construction work of Diversion Tunnel, Dam, Intake and Desilting Arrangement including Hydro-Mechanical works and Highway Tunnel was awarded to M/s Jaiprakash Associates Ltd. on June 26, 2011.

The Contract Package C-1 consists of following components:

  • 1 No. Diversion Tunnel of 12 m dia., 877.46 m length & 1118 Cumec. Design Discharge
  • Concrete Gravity Dam of 91 m height & 223.8 m length
  • U/s Coffer Dam of 168.75 m length & 22 m height
  • D/s Coffer Dam of 102.02 m length & 13.5 m height
  • Chute with Gates type Auxiliary Spillway with 1 No. gate
  • Sluice Spillway with 7 Nos. Gate, each of  8 m x 13.20 m
  • 4 Nos. Intake Tunnels each of 6.4 m dia. & total length of 1926.78 m
  • 4 Nos. underground Desilting Chambers each of 420 m (L) x 17/19 m (W) x 24.74 m (H)
  • Silt Flushing Tunnel(D-shaped) of size 3.6 m (W) x 2.96 m (H) to 8.6 m (W) x4.675 m (H), 495 m length
  • Highway Tunnel of 11 m dia., 1522 m length

Special Features / Uniqueness of the Package

  • Diversion Tunnels (with 12 M dia) constructed is the largest in the sub-continent.
  • Desilting Chambers are the biggest in size in the country.
  • First ever Highway Tunnel (1.5 KM) constructed in Bhutan on the National Highway.

Important dates

SL. No. Important Milestones Innaugration Details 
Dates
1. Punatsangchhu River was diverted through the Diversion Tunnel by Chief Advisior of Interim Government Hon’ble Lyonpo Sonam Tobgye. 20.05.2025
2. Dam concreting works commenced. 01.12.2017
3. Punatsangchhu River was diverted to its original course by Hon’ble Lyonpo Loknanth Sharma, Minister MoEA & His Excellenct Shri Sudhakar Delela, Ambassador of India to Bhutan. 21.12.2022
4. The dam concreting works successfully completed, paving way for subsequent phase of such reservior impoundment and power Genearation readiness. 22.10.2022
5. The reservoir filling commenced by the Hon’ble Prime Minister, Dasho Tshering Tobgay, along with the Minister for MoENR & the Ambassador of India to Bhutan. 21.02.2024
6. The reservoir reached its Full Reservoir Level (EL. 843m) marking a critical achievement in the project’s commissioning phase. 13.01.2025