PHYSICAL PROGRESS

 


PHYSICAL PROGRESS OF THE PROJECT AS ON Feburary 28, 2026

 

Item Status (%)
C-I Dam 100
C-II HRT (Head Race Tunnel) 100
C-III Power House 99.58
E&M Works (Electr0-mechanical) 99.90
Transmission 100.00
TOTAL 99.98